Date arithmetic ​

Introduction ​

These functions work in the date's own calendar and return a new date. Adding a month to a BS date gives the next BS month, not 30 days later and not the next AD month.

ts
import { addDays, addMonths, bsDate, formatDate } from '@nepdatejs/core';

const date = bsDate(2083, 7, 1);

formatDate(addDays(date, 10)); // → '2083-07-11'
formatDate(addMonths(date, 1)); // → '2083-08-01'

Your original date is never changed.

Adding and subtracting ​

addDays ​

Use a negative number to go back:

ts
import { addDays, bsDate, formatDate } from '@nepdatejs/core';

formatDate(addDays(bsDate(2083, 7, 1), -1)); // → '2083-06-31'
formatDate(addDays(bsDate(2083, 12, 30), 1)); // → '2084-01-01'

addMonths and addYears ​

BS months have different lengths, so a day might not exist in the target month. In that case the day is capped to the end of the month:

ts
import { addMonths, addYears, adDate, bsDate, formatDate } from '@nepdatejs/core';

formatDate(addMonths(bsDate(2083, 3, 32), 1)); // → '2083-04-31'
formatDate(addMonths(adDate(2026, 1, 31), 1)); // → '2026-02-28'
formatDate(addYears(adDate(2024, 2, 29), 1)); // → '2025-02-28'

Start and end of a period ​

ts
import {
  bsDate,
  endOfMonth,
  endOfWeek,
  endOfYear,
  formatDate,
  startOfMonth,
  startOfWeek,
  startOfYear,
} from '@nepdatejs/core';

const date = bsDate(2083, 7, 15);

formatDate(startOfMonth(date)); // → '2083-07-01'
formatDate(endOfMonth(date)); // → '2083-07-30'
formatDate(startOfYear(date)); // → '2083-01-01'
formatDate(endOfYear(date)); // → '2083-12-30'
formatDate(startOfWeek(date)); // → '2083-07-15'
formatDate(endOfWeek(date)); // → '2083-07-21'

Weeks start on Sunday in Nepal, which is the default. Pass a day from 0 (Sunday) to 6 (Saturday) to change it for one call, or set weekStartsOn with configure.

ts
import { bsDate, formatDate, startOfWeek } from '@nepdatejs/core';

formatDate(startOfWeek(bsDate(2083, 7, 15), 1)); // → '2083-07-09'

Differences ​

differenceInDays(a, b) is the number of days from b to a. It's positive when a is later, and the two dates may be in different calendars.

ts
import { adDate, bsDate, differenceInDays } from '@nepdatejs/core';

differenceInDays(bsDate(2083, 7, 10), bsDate(2083, 7, 1)); // → 9
differenceInDays(bsDate(2083, 7, 1), adDate(2026, 10, 18)); // → 0

To count a range including both ends, as for leave days, add one:

ts
import { bsDate, differenceInDays } from '@nepdatejs/core';

const start = bsDate(2083, 7, 1);
const end = bsDate(2083, 7, 5);

differenceInDays(end, start) + 1; // → 5

Going through days ​

eachDayOfMonth ​

Every day of a date's month, as a list:

ts
import { bsDate, eachDayOfMonth } from '@nepdatejs/core';

eachDayOfMonth(bsDate(2083, 7, 15)).length; // → 30

eachDayOfInterval ​

Every day from start to end, including both. It's a generator, so it stays cheap for long ranges. Use for...of, or spread it into a list:

ts
import { bsDate, eachDayOfInterval, formatDate, isWeekend } from '@nepdatejs/core';

const start = bsDate(2083, 7, 1);
const end = bsDate(2083, 7, 10);

[...eachDayOfInterval(start, end)].length; // → 10

let workingDays = 0;
for (const day of eachDayOfInterval(start, end)) {
  if (!isWeekend(day)) {
    workingDays++;
  }
}

workingDays; // → 9
formatDate(start); // → '2083-07-01'

Weekdays ​

dayOfWeek gives 0 for Sunday through 6 for Saturday. isWeekend uses the configured weekend, which is Saturday by default:

ts
import { bsDate, dayOfWeek, isWeekend } from '@nepdatejs/core';

const date = bsDate(2083, 7, 7);

dayOfWeek(date); // → 6
isWeekend(date); // → true
isWeekend(date, [0]); // → false